2013‐068
Orange Folder Review
1
Post-Hearing Questions for the Record
Submitted to the Honorable Joseph F. Bader
From Senator Ron Johnson
“Contract Management by the Department of Energy”
June 27, 2013
1. How many recommendations has the DNFSB made to DOE since it was created? Have
any not been accepted by DOE?
Board’s Response:
Over the 23-year period of 1990 to 2013, the Board has issued 57 Recommendations
to the Secretary of Energy. Only one of the Board’s Recommendations has been partially
rejected. This was Recommendation 2010-1, “Safety Analysis Requirements for Defining
Adequate Protection for the Public and Workers.” Currently, there are 12 open
Recommendations.
2. The hearing highlighted a number of cases, including the Hanford Waste Treatment Plant
and the Idaho National Lab Integrated Waste Treatment Unit where DNFSB
recommendations or other input received midway through a project caused delays and
cost increases. In your written testimony, you discussed DNFSB and DOE efforts since
2005 to better coordinate on review of safety design elements early in the process. How
have these efforts changed DNFSB involvement in project oversight since 2005? Please
provide an example of a project where DNFSB-DOE early collaboration has yielded
benefits.
Board’s Response:
Incorporating safety issues into project planning was the topic of a series of three
Board public hearings and meetings from December 7, 2005, and ending in March 22,
2007. The purpose of these public hearings and meetings was to discuss policies,
expectations, and processes for integrating safety into the design of DOE’s defense
nuclear facilities. The meetings were the result of the Board’s observation that DOE
demonstrated considerable difficulty integrating safety into the design of certain defense
nuclear facilities. DOE’s difficulties are attributed to the lack of integration of safety
during the design development process, development of design criteria, or proposed
designs that do not meet intended safety goals. In the 2007 public hearing and meeting
on safety-in-design, the Board recognized that there was uniform agreement with DOE
that implementation of safety at the earliest stages in the design of an environmental
clean-up or construction project is crucial to achieving mission related goals and
reducing cost increases and schedule delays.
A summary of how the efforts to identify and resolve safety issues early in the design
process changed DNFSB involvement in project oversight is contained in the July 19,
2007, “Report to Congress on the Status of Significant Unresolved Technical Differences
← American Bridge — Public Records
Post-Hearing Questions — Ron Johnson, Contract Management Review (2013)
Document text
2013‐068
Orange Folder Review
2
between the Board and the Department of Energy on Issues Concerning the Design and
Construction of DOE’s Defense Nuclear Facilities.” Enclosure (1) of that report
summarizes the actions the Board and DOE took to provide for more timely identification
and resolution of technical issues raised by the Board. These actions include the
following:
Issuance of “Project Letters” that summarize unresolved safety issues and the
Board’s view of the safety status of projects at appropriate critical decisions. For
example, Board Project Letters are typically issued as the project advances from
conceptual, to preliminary, and to final design. Starting in 2007, the Board has
issued 15 Project Letters on 10 different design and construction projects with the
latest being issued in July 2012.
Issuance of “Periodic Reports to Congress” that summarize to the Congress
unresolved safety issues on a project by project basis. To date, the Board has issued
19 Periodic Reports to Congress with the latest being issued in July 2013.
DOE updated DOE Order 413.3A, “Program and Project Management for the
Acquisition of Capital Assets,” which implements changes focused on early
integration of safety into design.
DOE implemented a new Standard 1189, “Integration of Safety into the Design
Process.” The standard implements specific actions during the project design phase
to achieve the safety-in-design objectives incorporated into DOE Order 413.3A.
DOE committed to updating Standard 1189 as part of the implementation plan to
resolve the Board’s Recommendation 2010-1, “Safety Analysis Requirements for
Defining Adequate Protection for the Public and the Workers.”
DOE and the Board selected two major projects, the Uranium Processing Facility
and the Integrated Waste Treatment Unit (IWTU), to demonstrate safety-in-design
requirements of Order 413.3A and Standard 1189.
DOE and the Board chose the IWTU at the Idaho National Laboratory to pilot the
integration of the safety and design initiative. In the Board’s view, the IWTU project
represents a good example of how the Board’s collaboration with DOE yielded positive
safety-related results. The Board issued two letters on IWTU, a Board Project Letter and
a Board Letter containing a staff issue report. In the first, a Project Letter dated
January 24, 2007, the Board stated that it did not have any significant safety issues
regarding the IWTU. However, the Board believed that several safety-related items
should be resolved prior to final design and construction. These items were reported as
open Board issues in the Board’s Periodic Reports to Congress from 2007 to 2009. The
Board documented DOE’s resolution of these issues in the Board’s February 9, 2009,
Periodic Report to Congress.
2013‐068
Orange Folder Review
3
The topic of the second Board Letter, dated May 1, 2008, addressed IWTU’s seismic
and structural design. The Board’s reviews revealed a number of issues related to the
development of the design basis ground motion and overall seismic design for the facility.
This letter further stated that as a result of significant efforts made by the DOE’s
Idaho Operations Office (DOE-ID) and the IWTU structural designer, Simpson,
Gumpertz & Heger, all issues were resolved and appropriate changes to the design were
made. The Board commended both DOE-ID and Simpson, Gumpertz & Heger for
resolving these issues in an expeditious manner. IWTU is currently progressing to the
hot commissioning stage of operations, which is anticipated for 2014.
3. In your testimony, you stated that while the DNFSB does not conduct cost-benefit
analyses of its recommendations, it does consider their “economic feasibility.” What
standard does the DNFSB use to assess economic feasibility?
Board’s Response:
The Board’s interpretation of the technical and economic feasibility of
Recommendations is documented in a February 14, 2013, report to the Chairmen and
Ranking Members of the Senate and House Armed Services Committees [copy enclosed].
The report states that each of the Board’s five members individually assess the economic
feasibility of a Recommendation based on careful consideration of the data, briefings,
and technical discussions held with/provided by DOE and the Board’s staff. The Board
considers economic feasibility by comparing the rough order of magnitude cost of
alternative approaches and structuring Recommendations so as to allow the Secretary
flexibility in designing cost-effective actions needed to address Board Recommendations.
The Board does not use a cost-benefit analysis formula. Congressional guidance on the
criterion for economic feasibility states that (1) the Board is not required “to make
formal findings concerning economic or technical feasibility”1 and (2) “the burden of
demonstrating that a Recommendation is not technically or economically feasible rests
with the Secretary.”2
Enclosure
1 S. REP. NO. 100‐173, at 28‐29 (1987).
2 Id.
Peter S. Winokur, Chairman DEFENSE NUCLEAR FACILITIES
Jessie H. Roberson, Vice Chairman SAFETY BOARD
John E. Mansfield Washington, DC 20004-2901
Joseph F. Bader
Sean Sullivan
February 14, 2013
The Honorable Carl Levin
Chairman
Senate Armed Services Committee
United States Senate
269 Russell Senate Office Building
Washington, DC 20510
The Honorable James Inhofe
Ranking Member
Senate Armed Services Committee
United States Senate
205 Russell Senate Office Building
Washington, DC 20510
Dear Chairman Levin and Ranking Member Inhofe:
The Joint Explanatory Statement of the Committee of Conference accompanying the Conference Report for the National Defense Authorization Act for Fiscal Year 2013 directed the Chairman of the Defense Nuclear Facilities Safety Board to "... submit a report to the congressional defense committees by February 15, 2013, regarding how the DNFSB considers the technical and economic feasibility of implementing its recommended measures." (Report, p. 394)
On behalf of the DNFSB, I am pleased to submit the report appended to this letter in response to the Conference Committee's direction.
Sincerely,
Peter S. Winokur, Ph.D.
Chairman
cc: The Hon. Ben Nelson, Chairman, Senate Armed Services Strategic Forces Subcommittee
The Hon. Jeff Sessions, Ranking Member, Senate Armed Services Strategic Forces
Subcommittee
Peter S. Winokur, Chairman
Jessie H. Roberson, Vice Chairman
John E. Mansfield
Joseph F. Bader
Sean Sullivan
DEFENSE NUCLEAR FACILITIES
SAFETY BOARD
Washington, DC 20004-2901
February 14, 2013
The Honorable Howard P. "Buck" McKeon
Chairman
House Armed Services Committee
United States House of Representatives
2310 Rayburn House Office Building
Washington, DC 20515
The Honorable Adam Smith
Ranking Member
House Armed Services Committee
United States House of Representatives
2264 Rayburn House Office Building
Washington, DC 20515
Dear Chairman McKeon and Ranking Member Smith:
The Joint Explanatory Statement of the Committee of Conference accompanying the Conference Report for the National Defense Authorization Act for Fiscal Year 2013 directed the Chairman of the Defense Nuclear Facilities Safety Board to "... submit a report to the congressional defense committees by February 15, 2013, regarding how the DNFSB considers the technical and economic feasibility of implementing its recommended measures." (Report, p. 394)
On behalf of the DNFSB, I am pleased to submit the report appended to this letter in response to the Conference Committee's direction.
Sincerely,
Peter S. Winokur, Ph.D.
Chairman
cc: The Hon. Mike Rogers, Chairman, House Armed Services Strategic Forces Subcommittee
The Hon. Jim Cooper, Ranking Member, House Armed Services Strategic Forces Subcommittee
Board Interpretation of "Technical and Economic Feasibility"
I. Introduction
The Board's enabling act, 42 U.S.C. § 2286 et seq., tasks the Board with issuing
recommendations to the Secretary of Energy regarding public health and safety at the
Department of Energy's (DOE's) defense nuclear facilities. Section 2286(a)(5) contains the
following requirement: "In making its recommendations, the Board shall consider the technical
and economic feasibility of implementing the recommended measures."¹ In this report, the
Board explains how it implements this statutory requirement.
II. Overview
It is the role of the five Board Members, nominated by the President and confirmed by
the Senate as recognized experts in nuclear safety matters, to individually make their own
decision on whether the recommendation they are considering is technically and economically
feasible. Such a decision is made based on a careful consideration by each Board Member
individually of the sum total of the information, data, briefings and technical discussions held
with/provided by DOE and Board staff. This material is made available over the considerable
period of time from initial consideration of a safety issue and whether it rises to the level of a
recommendation through final approval/denial of the proposed draft before the Board
Member.
The Board considers technical feasibility by ensuring that each recommendation is
capable of implementation using generally accepted scientific and engineering principles. The
Board considers economic feasibility by comparing the rough order of magnitude cost of
alternative approaches and structuring recommendations so as to allow the Secretary flexibility
in designing cost-effective actions needed to address Board recommendations. The Board does
not use a cost-benefit analysis formula.
The Board's consideration of technical and economic feasibility is guided by the
substantial legislative record surrounding the development and approval of the Board's
enabling act by Congress. The principal sponsor of the Board's enabling act in the late 1980s
was Senator John Glenn of Ohio, then Chairman of the Senate Committee on Governmental
Affairs. Senator Glenn introduced S. 1085, the "Nuclear Protections and Safety Act of 1987," in
April of 1987. The Committee on Governmental Affairs reported on the bill on September 24,
1987, in Senate Report 100-173 which addressed the subject of "technical and economic
feasibility," quoted in full below:
¹ This provision was recently amended by the National Defense Authorization Act for Fiscal Year 2013 to read: "In
making its recommendations, the Board shall consider, and specifically assess risk (whenever sufficient data exists),
the technical and economic feasibility of implementing the recommended measures" (emphasis added).
[I]n making its recommendations, the Board is directed to consider technical and economic feasibility. This is not a cost-benefit analysis formula. The Board's recommendations to substantially reduce the likelihood that events will occur at any DOE nuclear facilities should not be restricted by cost. Technical feasibility requires that the Board's recommendation be capable of implementation using generally accepted scientific and engineering principles. Addressing economic feasibility means that in seeking to reduce risks, the Board should compare the costs of alternative approaches so as to structure any recommendation in an economic manner. For example, the Board may determine that it will cost five hundred million dollars ($500,000,000) to reduce substantially the likelihood of a nuclear event at a twenty-year-old DOE production reactor, which has an expected useful life of twenty-three to twenty-five years and a replacement value of one billion dollars ($1,000,000,000). Under those circumstances, the Board could indicate what technical and engineering improvements would be needed to repair the existing facility so that it could achieve acceptable standards for continued operation, but recommend closing such an old facility and accelerating the planning and construction of a new, replacement facility as a more economic use of federal dollars.2
Fifth, subsection (g)(6)(A) directs the Board in making recommendations to consider technical and economic feasibility. This standard does not require the Board to make formal findings concerning economic or technical feasibility. It is further recognized that the Board's recommendations will never be subject to scientific or economic certainties or be without controversy. Inevitably there will be instances where the Secretary believes the Board has not properly evaluated the data and reached correct conclusions concerning the safety of DOE's facilities. In those instances where the Secretary believes the Board's recommendation addresses a non-existent or extremely remote technical possibility, and implementing the changes will be extremely burdensome, the Secretary may disagree with the Board utilizing subsections (h)(1)(A) and (h)(2)(B)(i). The burden of demonstrating that a recommendation is not technically or economically feasible rests with the Secretary. If the Secretary disagrees with the Board's recommendation on these grounds, subsection (h)(2)(B)(ii) requires the Secretary to report the disagreement to Congress and the President, along with the reasons for the Secretary's decision.3
S. 1085 was referred to the Senate Committee on Armed Services, then chaired by Senator Sam Nunn of Georgia. This committee reported on the bill on November 20, 1987. While the committee recommended a number of changes to the bill, it did not modify the "technical and economic feasibility" requirement for Board recommendations. The committee offered the following comment:
2 S. REP. No. 100-173, at 28-29 (1987).
3 Id. at 30.
2
[I]n making its recommendations, the Board is directed to consider technical and economic feasibility. Technical feasibility requires that the Board's recommendations be capable of implementation using generally accepted scientific and engineering principles. Economic feasibility means that the Board may compare the cost of alternative approaches and structure its recommendations so as to reflect cost comparisons. The Board may compare the costs of alternative approaches to achieving adequate protection of public health and safety. The Board may consider such factors as the remaining useful life of facilities, schedules and plans for replacing them, and means to mitigate disruptions to ongoing operations that may result from recommended safety improvements, and other considerations.4
The Board has followed the guidance provided by the Senate committees during the ensuing 23 years and 57 formal recommendations.
The following three general principles can be extracted from the committee reports:
* The requirement to consider technical and economic feasibility "is not a cost-benefit formula."5
* The Board is not required "to make formal findings concerning economic or technical feasibility."6
* "The burden of demonstrating that a recommendation is not technically or economically feasible rests with the Secretary."7
The first of these principles is a direct consequence of the enabling act requirement that the Board determine a recommendation is "necessary to ensure adequate protection of public health and safety."8 Hence, recommendations are not to concern safety above and beyond the Atomic Energy Act standard, but rather should look to achieving that standard of adequate protection. The courts have held that, unless required by statute, cost may not be weighed against measures needed to meet the statutory standard.9
The second and third principles are interrelated. The language of the statute directs the Board to "consider" technical and economic feasibility, yet Congress was aware that the Board would ultimately have to defer to the Secretary on application of these criteria. This is so because the Secretary is assigned the task of evaluating the Board's recommendations before drafting and providing to the Board an implementation plan. Part of this task involves deciding
4 S. REP. NO. 100-232, at 26 (1987).
5 supra note 1.
6 S. REP. NO. 100-173, at 28-29 (1987).
7 Id.
8 Id. at 5-7 (discussing the "adequate protection" standard to be used by the Board).
9 See Union of Concerned Scientists v. U.S. Nuclear Regulatory Comm'n, 880 F.2d 552 (D.C. Cir. 1989); Union of Concerned Scientists v. U.S. Nuclear Regulatory Comm'n, 824 F.2d 108 (D.C. Cir. 1987), reh'g en banc den. 859 F.2d 237.
3
the best means to implement the safety objectives set forth in the recommendation. It
therefore follows that the ultimate burden of deciding on technical and economic feasibility
properly rests with the Secretary.
III. Development of a Recommendation
Before moving to a discussion of the two separate criteria, it is important to explain how
the Board decides to issue a recommendation. Prior to the preparation of a recommendation,
the Board and its staff will have evaluated the safety implications as well as technical and
regulatory issues of concern. This evaluation is comprised of many activities: Board Member
and staff visits to affected sites; briefings to the Board by DOE and its contractors; exchanges of
formal correspondence; staff-to-staff meetings; reports to the Board submitted under a
reporting requirement; and, in some cases, public hearings. By the time a recommendation is
considered, DOE will be fully aware of the Board's concerns and will have provided much of the
information relied on by the Board to formulate its position. None of the Board's 57
recommendations have been issued without this level of review and analysis.
The Board applies its deep understanding of DOE's nuclear facilities, underlying
technologies, programs, standards, and procedures to avoid recommending measures that
simply cannot be implemented. The Board has always been pragmatic in its review of
alternative means and methods proposed by DOE to meet the intent of a recommendation. In
the great majority of cases, DOE has been able to develop an implementation plan suitable to
address the safety problems of concern to the Board. However, disagreements have arisen over
priorities, risks, and safety criteria. These disagreements were expected by Congress:
"Inevitably there will be instances where the Secretary believes the Board has not properly
evaluated the data and reached correct conclusions concerning the safety of DOE's facilities."10
All regulatory and oversight systems involve tension over complex problems. The Board
believes that the best approach to satisfying Congressional intent is to be extremely thorough
in exploring safety concerns prior to considering whether a recommendation to the Secretary is
needed.
IV. Technical Feasibility
Both Senate reports include the same criterion for technical feasibility: is the
recommended measure "capable of implementation using generally accepted scientific and
engineering principles"?11 This criterion would apply principally in cases where the Board
recommends that DOE take specific physical actions such as installing new equipment,
upgrading a safety system, engaging in a test program, and the like, as opposed to setting out a
desired result without specifying means. Of its recommendations issued to date, 10 fall into this
category.12 In its other 47 recommendations, the Board is recommending that DOE address
10 S. REP. NO. 100-173, at 28-29 (1987).
11 supra note 1; id. at 30.
12 Recommendations 90-1, 90-3, 90-7, 93-5, 95-1, 2000-1, 2004-2, 2010-2, 2012-1, 2012-2.
4
concerns in its safety framework, including safety management programs dealing with fire
protection, quality assurance, confinement ventilation, packaging, and administrative controls.
Assurance of technical feasibility of recommended measures is provided by three
factors. First, the Board Members themselves are legally required to be recognized experts in
the field of nuclear safety and thus trained in physics, chemistry, nuclear engineering, and
mathematics. Second, the Board has recruited and maintains a technical staff holding advanced
degrees in nearly every technical discipline applicable to defense nuclear facilities. Outside
experts are regularly engaged (as authorized by the Board's enabling legislation) whenever
specialized knowledge is required. Third, the corporate knowledge represented by the Board
Members and its staff extends into every field of nuclear science and engineering, from theory
through to implementation, including construction, operations, and project management.
Taken together, these factors enable the Board to assure that prior to issuing a
recommendation, the technical measures necessary to address the recommendation are
readily available should DOE choose to implement them. Specific examples of recent
recommendations are included in Section VI below.
Additional assurance is provided by the fact that the Secretary has not responded to any
Board recommendation by arguing that the measures requested by the Board are "technically
infeasible." This record gives the Board confidence that it has faithfully followed the guidance
of Congress to recommend measures "capable of implementation using generally accepted
scientific and engineering principles."
V. Economic Feasibility
Congressional guidance on this criterion can be summarized in these three points:
* The burden of demonstrating that a recommended measure "will be extremely
burdensome" to implement rests with the Secretary.13
* The Board may compare the cost of alternative approaches and structure its
recommendations so as to reflect cost comparisons.
* The Board may consider such factors as the remaining useful life of facilities, schedules
and plans for replacing them, and means to mitigate disruptions to ongoing operations
that may result from recommended safety improvements, and other considerations.
The reason for the first of these has already been noted: only DOE can estimate with any
accuracy the precise cost of implementing Board recommendations. In most recommendations
the Board identifies a safety concern and safety objectives, but leaves up to the Secretary what
specific actions will be taken. Moreover, the Board lacks the resources, expertise, and
information base on which to make financial estimates.
13 S. REP. NO. 100-173, at 28-29 (1987).
5
In formulating the specifics of its recommendations and evaluating implementation
plans, the Board does take into account such factors as "the remaining useful life of facilities,
schedules and plans for replacing them, and means to mitigate disruptions to ongoing
operations that may result from recommended safety improvements,"14 and other
considerations. Sometimes, the Board considers safety issues in an old DOE facility that may not
be replaced for some years, if ever.15 A recent example is the Board's consideration of newly-
discovered seismic deficiencies which led to Recommendation 2009-2, Los Alamos National
Laboratory Plutonium Facility Seismic Safety.16
Near-term actions and compensatory measures to reduce significantly the
consequences of seismically induced events will likely involve operating the
facility with restrictions on material-at-risk, removing inventory from susceptible
locations or storing material in robust containers, and reducing the likelihood of
a fire following a seismic event by identifying and implementing appropriate
safety measures. Consistent with the Board 's Recommendation 2004-2, Active
Confinement Systems, one long-term strategy that could provide effective
mitigation for seismic events involves upgrading the facility's confinement
ventilation system to meet seismic performance category 3 criteria. This strategy
would allow the confinement ventilation system to reduce reliably the
consequences of a seismically induced event by many orders of magnitude to
acceptably low values.
When NNSA learned of a significant increase in the estimated ground motion
that the Los Alamos Plutonium Facility could experience during an earthquake, the
Board carefully considered the subsequent dose consequence to the public following
such an event. The Board then purposely crafted Recommendation 2009-2 so as to give
the Secretary maximum latitude to choose the most effective remedies. A wide range
of economically-feasible remedies were considered by the Board, including reduction of
material-at-risk (MAR), changes in facility operations, and facility replacement.
Recommendation 2009-2 identified the severity and urgency of the situation and called
for an acceptable safety strategy involving both immediate and long term actions to
reduce this risk. As noted above, the Board recommended that installation of an active
confinement ventilation system be considered as part of an effective long-term strategy
for risk-reduction. In short, the Board identified the risk to the public, and further
14 Budget Request for Department of Energy Atomic Energy Defense Activities and Department of Defense Nuclear
Forces Program: Hearing Before the Subcomm. on Strategic Forces of the H. Comm. on Armed Services, 112th Cong.
5-6 (2011) (statement of Dr. Peter S. Winokur, Chairman, Defense Nuclear Facilities Safety Board).
15 Congress expected this situation to occur: "Under those circumstances, the Board could indicate what technical
and engineering improvements would be needed to repair the existing facility so that it could achieve acceptable
standards for continued operation, but recommend closing such an old facility and accelerating the planning and
construction of a new, replacement facility as a more economic use of federal dollars." S. Rep. No. 100-173, at 28-
29 (1987).
16 Issued October 26, 2009.
6
identified a wide range of economically-feasible remedies, then left it to the Secretary
to select the specific remedial measures and timetable for implementation.
VI. Application of Principles to Recent Recommendations
In 2012 the Board issued two recommendations, both dealing with highly technical
problems at defense nuclear facilities. On May 9, 2012, the Board transmitted
Recommendation 2012-1, Savannah River Site Building 235-F Safety, to the Secretary of Energy.
This recommendation dealt with removing plutonium-238 (Pu-238) contamination from an
inactive facility. Recommendation 2012-2, Hanford Tank Farms Flammable Gas Safety Strategy,
sent to the Secretary on September 28, 2012, addressed a serious safety problem at the
Hanford Tank Farms. In both cases, the Board was fully informed as to the nature of the safety
problem and recommended technically and economically feasible measures that should resolve
the issues in a reasonable period of time.
Recommendation 2012-1
Building 235-F at the Savannah River Site no longer has a programmatic mission. It is
operated in a surveillance and maintenance mode, is normally unoccupied, and houses several
partially deactivated processing lines. With the exception of residual contamination, Building
235-F has been de-inventoried of special nuclear material. This residual contamination
constitutes the principal hazard and includes a significant quantity of Pu-238. Pu-238 in this
facility is in the form of highly dispersible, fine powder. This form increases the potential dose
consequences associated with a release.
The Board first identified the need to remove Pu-238 from Building 235-F in a 2003
letter to the Secretary of Energy: "In particular, Building 235-F was anticipated to be shut down
in the near future, but now is planned to be used for long-term storage and related
operations...the risk from several hazards ha[s] been accepted rather than eliminated (e.g.,
combustible inactive cables in KAMS and ... plutonium-238 contamination in Building 235-F)."17
Later in 2003, the Board filed a special report requested by Congress. The Board stated in
regard to this same facility:
DOE should carry out its plan to remove and characterize plutonium materials currently
stored in 235-F. DOE should not plan extended storage of plutonium in 235-F until it has
completed implementing the proposals in this report. It may be preferable from safety,
cost, and mission perspectives to pursue storage elsewhere at SRS. Options include an
enhanced KAMS facility, a new storage facility, or an expanded PDCF.18
17 Letter from John T. Conway, Chairman, Defense Nuclear Facilities Safety Board, to the Hon. E. Spencer Abraham,
Secretary, U.S. Dep't of Energy (June 12, 2003). This letter was based on several years of work by the Board's
technical staff in the form of onsite inspections of Building 235-F and review of DOE's documentation of the
building's radioactive inventory.
18 DEFENSE NUCLEAR FACILITIES SAFETY BOARD, STUDY OF FACILITIES FOR STORAGE OF PLUTONIUM AND PLUTONIUM MATERIALS AT
SAVANNAH RIVER SITE 2-5 (2003).
7
The Board reiterated this concern in a second report to Congress in 2005. In that report,
the Board stated:
The Board notes that DOE-SR intends to continue making some structural and
equipment upgrades to 235-F. DOE-SR considers these upgrades necessary to provide
confinement of plutonium-238 holdup in old processing cells should there be a
significant earthquake. The presence of extensive plutonium-238 holdup is one of the
most significant hazards in 235-F. The Board believes the first priority for DOE-SR should
be to decontaminate the process cells to eliminate this hazard. Any structural or
equipment improvements would be warranted only if the effort to decontaminate the
plutonium-238 holdup were protracted. The Board will continue to follow this issue in
the course of its normal safety oversight for the site.19
On a number of occasions from 2005 to 2012, DOE evaluated options and developed
plans to remove Pu-238 residual contamination from this facility. However, because these
efforts never moved beyond the planning stage, the Board found it necessary to recommend
that the Secretary take action to reduce the radiological hazard of this deteriorating facility. By
2012, the Board and its staff had been involved in the technical issues presented for more than
a decade. During that period, the Board had the opportunity to review DOE's own plans for Pu-
238 decontamination, plans that were never put into effect. The Board became increasingly
concerned that ventilation and fire protection systems were continuing to degrade. In addition,
the construction of the MOX facility in recent years had placed many additional workers at risk.
Recommendation 2012-1 thus identified the need for DOE to take near-term actions to
more effectively prevent a major fire in Building 235-F and to take action to remove and/or
immobilize the residual contamination within Building 235-F because of the potential dose
consequences to collocated workers and the public.
As regards to technical feasibility, the Board recommended near-term actions to reduce
the fire hazards in Building 235-F from combustibles and electrical ignition sources. The Board
pointed to a September 2011 walkdown of Building 235-F by Board staff that specifically
identified a significant quantity of transient and fixed combustibles and unnecessary, non-air
gapped electrical equipment. Remedial measures clearly involved generally accepted practices.
The recommendation further addressed hazards associated with residual contamination. The
Board understood that immobilization and/or removal of the hazardous material involved
standard engineering practices.
As regards economic feasibility, the Board considered DOE's previous evaluations and
plans to immobilize and/or remove residual Pu-238 contamination. The Board further
understood that as an alternative to immobilization/removal of residual contamination,
19 DEFENSE NUCLEAR FACILITIES SAFETY BOARD, STUDY OF FACILITIES FOR STORAGE OF PLUTONIUM AND PLUTONIUM MATERIALS AT
SAVANNAH RIVER SITE 2-4 (2005).
8
physical upgrades to fire and ventilation safety systems could also have resulted in adequate
protection. However, given the lack of facility mission and remaining life, and the likelihood
that immobilization/removal would ultimately be necessary, physical upgrades (other than
early warning smoke and fire alarms) were understood to be economically inefficient.
Accordingly, Recommendation 2012-1 advised the Secretary to take immediate, low cost
actions such as removal of combustibles, de-energization and air-gapping of electrical ignition
sources, evaluation of early detection alarm systems, and upgrades to the emergency response
plan. The Secretary was further advised to immobilize or remove residual contamination as a
long-term measure by whatever method the Secretary found to be most efficient and effective.
On July 10, 2012, the Secretary of Energy accepted the recommendation. In his
acceptance letter, the Secretary stated:
DOE agrees with the Board that action must be taken to reduce the hazards associated
with the material at risk that remains as residual contamination within Building 235-F.
The Board acknowledged in its letter that DOE has taken action to de-inventory Building
235-F of special nuclear material. DOE has also taken action to remove the transient
combustible material within Building 235-F and to limit access. In developing an
Implementation Plan, DOE will address all sub-recommendations with the ultimate goal
of reducing, to the extent feasible, the radiological hazards from residual contamination
and the fire hazards due to excessive combustible materials and electrical ignition
sources . . . We look forward to working with the Board as we work to reduce the
hazards posed by Building 235-F.20
The Board is now reviewing DOE's implementation plan, submitted on December 5,
2012. The plan identifies no areas of the recommendation that, in DOE's view, are technically or
economically infeasible.
Recommendation 2012-2
In this recommendation, the Board requested that DOE take a number of specific
actions to reduce the accident threat posed by flammable gases in storage tanks at the Hanford
Tank Farms. The ventilation systems for the double-shell tanks (DST's) in the Tank Farms are
important in preventing and mitigating potential accidents involving the flammable gases
generated by the high-level wastes stored in these tanks. The Tank Farms safety analysis shows
that many of the tanks contain sufficient quantities of gas trapped in the waste such that
flammability limits could be exceeded if the gases were spontaneously released, which is
possible under both normal operating and accident conditions. Furthermore, all the double-
shell tanks contain wastes that continuously generate flammable gases and would eventually
create a flammable atmosphere in the tank without adequate ventilation. Consequently,
ventilating the double-shell tanks will prevent hydrogen explosions in the vessel headspace.
20 Letter from the Hon. Steven Chu, Secretary, U.S. Dep't of Energy, to Dr. Peter S. Winokur, Chairman, Defense
Nuclear Facilities Safety Board (July 10, 2012).
9
Tank ventilation has been the preferred safety strategy to adequately protect collocated
workers and the public for most of the past two decades.
In 2010, DOE approved downgrading the functional classification of the ventilation
systems from safety-significant to general service. In lieu of a credited engineered feature, DOE
implemented an administrative control to monitor flammable gas conditions in the tanks.
However, the Board identified a number of weaknesses with the administrative control,
including the need to effectively measure flow rates in the ventilation system. The weaknesses
collectively rendered the control inadequate to perform the specified safety function. The
Board further noted that other engineered systems providing indications used in determining
whether operators need to take corrective action were not classified as safety significant and
would not be qualified or maintained by DOE in accordance with their safety function. The
Board documented its concerns in a letter to DOE on August 5, 2010.
In response, DOE issued a letter to the Board on February 25, 2011, stating that it would
take action to restore the double-shell tank ventilation systems to safety-significant status and
upgrade other monitoring systems to safety-significant status. However, DOE did not make
meaningful progress in accomplishing these important commitments. The Board therefore
issued Recommendation 2012-2 to bring the issue to the attention of the Secretary.
As regards to technical feasibility, the Board considered the nature and severity of the
flammable gas hazards in the Hanford DSTs, the reliability of DOE's chosen safety strategy,
and DOE's applicable safety requirements. The Board's recommendation considered that active
confinement ventilation is the most effective engineering solution used to prevent the build-up
of flammable gases in radioactive waste storage vessels. The technical feasibility of the
recommendation was self-evident in that the ventilation systems already existed and had been
previously credited and relied upon to perform this vital safety function at the Tank Farms.
As regards to the economic feasibility, the Board specifically recommended that DOE
use a graded approach and "... determine the necessary attributes of an adequate active
ventilation system that can deliver the required flow rates within the time frame necessary to
prevent and mitigate the site-specific flammable gas hazards at the Hanford Tank Farms." In
this regard, the Board was sensitive to the costs of recommending extensive upgrades to the
existing system. The Board's recommendation recognized that the primary considerations
involved reliable flow monitoring and assurance of the prescribed flow rates. Consequently,
the Board recommended installing safety related flow monitoring in the tank farm ventilation
system and restoring safety related maintenance and testing requirements to the installed
active ventilation systems to assure that the required flow rates were met.
The Secretary accepted Recommendation 2012-2 in these terms:
In developing an Implementation Plan (IP), DOE will take the pragmatic and graded
approach detailed below to address the sub recommendations that will significantly
improve the robustness of flammable gas controls in the near term. DOE is confident
10
this is the most expeditious approach to implement a more robust safety control for
Double Shell Tank (DST) ventilation monitoring consistent with the intent of
Recommendation 2012-2.
* * * *
DOE is committed to the safe operation of its nuclear facilities consistent with the
principles of Integrated Safety Management and the Department's nuclear safety
requirements. DOE values the Board's input on how the Department can improve its
activities. We look forward to working with the Board and its staff on preparing DOE's
IP for Recommendation 2012-2.21
From these statements it appears that DOE is confident the recommendation can be
implemented using a "pragmatic and graded approach" that will fully satisfy the Board's safety
objectives. The plan identifies no areas of the recommendation that, in DOE's view, are
technically or economically infeasible.
VII. Conclusion
Over a period of some 23 years, the Board has endeavored to follow the guidance
provided by Congress in applying the statutory requirement to consider "technical and
economic feasibility." Proof that the Board has succeeded rests in the fact the Secretary has
accepted every Board recommendation in whole or in part; partial acceptances have not been
based on failure to meet the technical and economic feasibility criteria. The Board will continue
in every case to pragmatically search for technically sound and economically feasible solutions
to safety concerns at defense nuclear facilities, while being mindful of the ultimate requirement
that adequate protection be provided to the public.
21 Letter from the Hon. Steven Chu, Secretary, U.S. Dep't of Energy, to Dr. Peter S. Winokur, Chairman, Defense
Nuclear Facilities Safety Board (Jan. 7, 2013).
11
2013‐068
Orange Folder Review
RECORDS CONCURRENCE FORM
NUMBER
FY2013-
SUBJECT
Board Response to Post-Hearing Questions for the Record Submitted to the
Honorable Joseph F. Bader from Senator Ron Johnson
GROUP LEADER CONCURRENCE (Signature and Date)
DNFSB STRATEGIC ACTION PLAN REFERENCE:
TECHNICAL CONCURRENCE
GENERAL MANAGER
CONCURRENCE
LEGAL CONCURRENCE
TECHNICAL EDITOR
ACTING TECHNICAL
DIRECTOR
GENERAL MANAGER
GENERAL COUNSEL
NAME
NAME: S.A. STOKES
NAME: M. ATWOOD
NAME: D.S. JONAS
INITIALS:
INITIALS:
INITIALS:
INITIALS:
DATE:
DATE:
DATE:
DATE:
DEPUTY TECHNICAL DIRECTOR
FOR SITE REPS
BOARD BRIEFING
BRIEF TO BOARD MEMBERS
NAME: R.E. TONTODONATO
NAME: S.A. STOKES
INITIALS:
INITIALS:
DATE:
DATE:
CLASSIFICATION CHECK
BOARD MEMBERS (5), W/ ENCLOSURE
OGC, W/ ENCLOSURE
OGM, W/ ENCLOSURE
OTD, W/ ENCLOSURE
SITE REPS, W/ ENCLOSURE (EMAIL)
ARCHIVES/CHRON.,(2), W/ ENCLOSURE
LOG KEEPER, W/ ENCLOSURE
DNFSB SECURITY
MICHAEL LEGGETT
DOCUMENT #1
DOCUMENT #2
DOCUMENT #3
DNFSB CONTROL
NUMBER
DNFSB CONTROL
NUMBER
DNFSB CONTROL
NUMBER
DATE CLEARED BY
DOE
DATE CLEARED BY
DOE
DATE CLEARED BY
DOE
INITIALS
INITIALS
INITIALS
DATE
DATE
DATE
TRANSFER FILE NAME
H:\Home\Transfer\LETTERS\NFDI-FY13\NFDIL058.13.docx
SECRETARY/AUTHOR
Billings/Poloski
RELEASED FOR DISTRIBUTION ON